Ashby Highrise: Stuck on the Dock

   

That last city permit is proving difficult for developers of the Ashby Highrise, as the city denied the variance request for a loading dock last week: “In comments for the Public Works and Engineering Department, city engineer Mark Loethen said the at-grade loading dock from Bissonnet Street will not be allowed because its use would obstruct lanes of traffic. In his Sept. 4 comments, Loethen said the variance was rejected for the same reason, citing Sec. 40-86 of the code of ordinances. ‘Such a driveway, as proposed, would excessively interfere with the normal use of the Bissonnet Street right of way,’ he said.” [West University Examiner; previously]